Answer FileConstruction
What are the mechanics lien deadlines in California?
Three dates decide everything. First, the preliminary notice: subcontractors and suppliers must serve a 20-day preliminary notice on the owner, direct contractor, and lender to preserve lien rights for work already performed and everything after (Civil Code section 8204) — late notice protects only the prior 20 days of work. Second, recording: after finishing work, a direct contractor must record the lien within 90 days of completion of the whole project, shortened to 60 days if the owner records a notice of completion; other claimants get 90 or 30 days respectively (sections 8412, 8414). Third, foreclosure: a lawsuit to enforce the lien must be filed within 90 days of recording, or the lien expires by operation of law (section 8460). On public works, where private land cannot be liened, the parallel remedies are the stop payment notice (Civil Code section 9350 et seq.) and payment bond claims. The lattice is unforgiving — calendaring the dates at the start of a project is the whole game.
Authority: Cal. Civ. Code § 8412
Legal information, not legal advice.
More from this answer file
Counsel for this matter
Read the record. Then decide.
Describe your matter once, weigh the published scores, and place the call — the choice is always yours.
Find Your Counsel195,000+ attorneys · 58 counties · Scored in the open